To: All Tenants
From: Sarah Ricardo, Assistant Property Manager
Subject: CBC Entrance (Restoration Project)
Please be advised that Chancelot Concrete Restoration will be re-waterproofing the entrance at CBC. The work entails removing the existing topping concrete, fill, and membrane. Replacing any delaminated portions on the structural slab with new concrete and rebar, applying a new membrane, and adding new fill and topping slab.
Project Start Date: August 9, 2021
Project End Date: October 15, 2021
Impact to Mall: Access to the entrance will be maintained at all times for the duration of the project with hoarding and ramps.
Should you have any questions or concerns, please do not hesitate to contact Sarah Ricardo, Assistant Property Manager, directly at 587-340-4910 or sricardo@edmontoncitycentre.com.
Sincerely,
Edmonton City Centre