To: All Tenants
From: Susan Radford, Assistant Property Manager
Subject: LRT Updates

The Valley Line LRT Spring Stakeholder Meeting has taken place with the following key updates as it pertains to Edmonton City Centre:

• Reminder: Closure of 102 Avenue will remain in place into mid 2021.

• Schedule & Overall:
o Testing of the SE portion (over the Whitemud and up to Roper Road) will commence this Spring.
o Construction of the Davies stop is now underway.
o Utilities and Electrical OCS lines are now complete and reinforced up to Bonnie Doon.
o The demo unit is being relocated from Bonnie Doon to Millwoods Town Centre this Spring.
o The conversion of the Connors Road traffic circle to an intersection will take place this year.

• 102 Avenue: Sidewalk closures will continue intermittently throughout 2019.
o Considerations to ECC’s entrances and emergency exits are being accommodated.
o As sidewalk work approaches each ECC entrance along 102 Avenue, work will be phased in such a way that at least half of any entrance is kept open and accessible at any time.

• Churchill: will continue to see extensive construction throughout 2019 as they create the ‘HUB’ that connects new and existing lines.
o Festivals (The Works, Street Performers, etc.) will remain relocated for the 2019 festival season.
Plans for 2020 will be confirmed by end of September.
We thank you for your continued patience and partnership while City completes this project, and encourage you to reach out to the City of Edmonton, 311 Call Centre with any questions or concerns.

Sincerely,
OXFORD PROPERTIES GROUP
Susan Radford, Assistant Property Manager